Installation

This installation task list is intended to be used as a planning guide only. Relevant Australian Standards must be followed (see earlier section on installation checklists). Where it varies to this list, manufacturers installation procedure should be followed. By no means are these tasks exhaustive, and additional tasks can improve quality. Tasks may be performed in other orders as required by each job. A single string array is assumed. A licensed electrician is assumed to be undertaking these tasks, as Low Voltages (>120V DC) are typically involved.

 

Tasks

Planning

     

  1. Assess Safety
  2. Assess optimal panel placement

  3. Assess optimal inverter placement

  4. Assess roof penetration location (if needed)

  5. Assess cable routes

  6. Test panel Voc & Isc

  7. Record panel serial numbers

  8. Remove panels from boxes and place at panel lift location

Rooftop

     

  1. Undertake safety measures as required throughout this process
  2. Join rails

  3. Place rails in location

  4. Affix feet to roof, using rubber pads for galvanic isolation on metal roofs, or grinding back tile underside if necessary

  5. Affix rails to feet, ensuring rails are level

  6. If necessary, penetrate roof and apply dektite

  7. If junction box to be used, affix junction box to rails near end of panels closest to inverter

  8. Working from end of array furthest from inverter,

    1. Place panel perpendicular to rails
    2. If at beginning of row/string then connect runback cable to panels connector, otherwise connect previous and current panels connectors
    3. Neatly cable tie panels cable and runback cable to rails, enclosing in conduit if preferred
    4. Lay panel flat on rails, ensure it is level and parallel with rest of array, and secure with end clamp and/or mid clamps
    5. Repeat a) through d) until working on final panel
    6. Prior to securing final panel, connect cables to (junction box, circuit breaker, or fuses if applicable) and DC feed cable, which electrician should have routed by now. Each strings voltage and current should be tested as part of commissioning procedure.
    7. Tidy up panel alignment and ensure panels are secure
  9. Ensure waterproof entry and proper mechanical protection of feed wire

  10. Earth array frames if necessary

  11. Tidy up site

Inverter

  1. Undertake safety measures as required throughout this process

  2. Run DC cable (identified as Solar DC) from inverter location to solar array, via roof penetration if applicable

  3. Run AC cable from switchboard to inverter

  4. Neatly affix conduit and clamps for DC and AC cabling runs

  5. Affix inverter enclosure to wall (if applicable)

  6. Affix inverter to wall or enclosure (if applicable)

  7. Affix DC breaker enclosure nearby

  8. Affix DC feed wires into DC breaker

  9. Affix DC inverter inputs into DC breaker

  10. Secure DC breaker into enclosure

  11. Affix inverter AC plug onto AC cable

  12. Earth inverter enclosure if necessary

  13. Connect array frame earth to inverter earth if necessary

  14. Affix AC breaker (and enclosure if necessary) to switchboard

  15. Switch normal power supply off

  16. Connect AC cable to non-RCD protected consumer side of normal supply main switch

  17. Switch normal power supply on

  18. Test DC input polarity

  19. Affix signage and labels as appropriate

  20. Test and commission system

  21. Tidy up site

  22. Issue certificate of electrical safety or equivalent

  23. Arrange for system inspection and meter change over as required in local electricity distribution area.

     

Bill of Materials

  • Panels

  • Inverter

    • Inverter enclosure if required
  • Framing

    • End clamps
    • Mid Clamps
    • Rails
    • Rail Joiners
    • Feet
    • Rubber pad (for galvanic isolation)
    • Roof screws
  • DC connection

    • DC Connectors (preferred) or Crimps/Solder/Lugs
    • Junction box (optional on arrays with 1-2 strings)
    • Double adapter (for 2 stringed arrays)
    • Heat Shrink (& heat gun)
  • AC isolation

    • AC circuit breaker and enclosure
  • DC isolation

    • Load breaking: DC circuit breaker & enclosure
    • Non load-breaking Fuse & Fuse holder (if required)
  • Fault current protection (if > 2 strings)

  • Waterproofing

    • Dektite
    • Silicone
  • Wire (& marking pen if not marked "solar DC")

    • AC between inverter and switchboard
    • DC runback from far end of array
    • DC feed cable to inverter
  • Signage

    • Solar Supply Main Switch or equivalent
    • Normal Supply Main Switch or equivalent
    • Solar Array Isolator or equivalent
    • Shutdown Procedure
    • Warning Dual Supply (& extras for connection to distribution board)
    • Solar Array on Roof
    • Inverter location (if not visible from meterboard)
    • Solar DC (if junction boxes used)
  • Conduit

  • Fixings

    • Inverter (& enclosure if required)
    • Signage
    • Conduit clamps & screws
    • Cable ties
    • Circuit breaker enclosures.
  • Operations Manual

    Future Sustainability are Master Electricians, the peak electrical body for Queensland based electrical Contractors.


Bookmark this page DIGG this site Share this site
Made by QMG